Process Step | Date Initiated | Date Completed | Comments |
Received | 6/11/2014 | 6/11/2014 |
|
WMR Request | 6/16/2014 | 6/17/2014 |
|
Transfer Initial Comment Period | 6/17/2014 | 7/18/2014 |
|
Reimbursement Authority | 10/17/2014 | |
|
RA Applicant Agreement | 11/17/2014 | 11/17/2014 |
|
Draft PD Issued | 4/22/2015 | 4/22/2015 |
|
PD Issued | 5/8/2015 | 5/8/2015 |
|
PD Weekly Public Notice | 5/12/2015 | 5/12/2015 |
|
Final Order Issued | 6/12/2015 | 6/12/2015 |
|
CBU Received | 4/30/2018 | 4/30/2018 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
Certificate Confirming Issued | 5/9/2019 | 5/9/2019 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|