Process Step | Date Initiated | Date Completed | Comments |
Received | 6/16/2014 | 6/16/2014 |
|
WMR Request | 6/23/2014 | 7/18/2014 |
|
GW Review Request | 6/23/2014 | 4/1/2015 |
|
Transfer Initial Comment Period | 6/24/2014 | 7/25/2014 |
|
Draft PD Issued | 4/21/2015 | 4/21/2015 |
|
PD Issued | 5/7/2015 | 5/7/2015 |
|
PD Weekly Public Notice | 5/12/2015 | 5/12/2015 |
|
Final Order Issued | 6/11/2015 | 6/11/2015 |
|
Certificate Remaining Issued | 6/11/2015 | 6/11/2015 |
90420 issued supersedes 46732
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
Extension Application Received | 11/29/2018 | 11/29/2018 |
|
Extension FO Issued | 12/11/2018 | 12/11/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
CBU Completeness Review | 9/25/2020 | 10/9/2020 |
|
CBU Received (Partial) | 9/25/2020 | 9/25/2020 |
|
Extended Completion Date [Extension C Date] | 10/1/2020 | 10/1/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|
Extension Application Received | 6/17/2022 | 6/17/2022 |
|
Extension FO Issued | 8/10/2022 | 8/10/2022 |
|
Extended Completion Date [Extension C Date] | 10/1/2023 | 10/1/2023 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|