Process Step | Date Initiated | Date Completed | Comments |
Received | 6/18/2014 | 6/18/2014 |
|
WMR Request | 6/23/2014 | 7/21/2014 |
|
GW Review Request | 6/23/2014 | 8/25/2014 |
|
Transfer Initial Comment Period | 6/24/2014 | 7/25/2014 |
|
Draft PD Issued | 12/4/2014 | 12/4/2014 |
|
PD Issued | 2/17/2015 | 2/17/2015 |
|
PD Weekly Public Notice | 2/24/2015 | 2/24/2015 |
|
Final Order Issued | 4/2/2015 | 4/2/2015 |
|
Certificate Remaining Issued | 4/2/2015 | 4/2/2015 |
90146 issued supersedes 64015
|
CBU Received | 10/5/2015 | 10/5/2015 |
|
Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
CBU Due | 10/1/2017 | 10/1/2017 |
|
Certificate Confirming Issued | 12/27/2019 | 12/27/2019 |
|