Process Step | Date Initiated | Date Completed | Comments |
Received | 9/24/2014 | 9/24/2014 |
|
WMR Request | 9/26/2014 | 10/8/2014 |
|
ODFW Review | 9/26/2014 | 10/22/2014 |
|
Transfer Initial Comment Period | 9/30/2014 | 10/31/2014 |
|
Draft PD Issued | 12/12/2014 | 12/12/2014 |
|
PD Issued | 2/26/2015 | 2/26/2015 |
|
PD Weekly Public Notice | 3/3/2015 | 3/3/2015 |
|
Final Order Issued | 5/14/2015 | 5/14/2015 |
|
Certificate Confirming Issued | 5/14/2015 | 5/14/2015 |
89997 issued supersedes 48423
|
Final Order Issued | 1/21/2016 | 1/21/2016 |
|
Extension FO Issued | 5/25/2018 | 5/25/2018 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|