| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/4/2014 | 11/4/2014 |
|
| WMR Request | 11/7/2014 | 11/13/2014 |
|
| GW Review Request | 11/7/2014 | 3/9/2015 |
|
| Transfer Initial Comment Period | 11/11/2014 | 12/12/2014 |
|
| Draft PD Issued | 4/1/2015 | 4/1/2015 |
|
| PD Issued | 5/27/2015 | 5/27/2015 |
|
| PD Weekly Public Notice | 6/2/2015 | 6/2/2015 |
|
| Final Order Issued | 8/4/2015 | 8/4/2015 |
|
| Certificate Remaining Issued | 8/4/2015 | 8/4/2015 |
90596 issued supersedes 89881
|
| Certificate Remaining Issued | 12/14/2015 | 12/14/2015 |
91059 issued supersedes 90596
|
| CBU Received | 3/7/2016 | 3/7/2016 |
|
| CBU Due | 10/1/2016 | 10/1/2016 |
|
| Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|