| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/1/2014 | 12/1/2014 |
|
| WMR Request | 12/8/2014 | 1/8/2015 |
|
| GW Review Request | 12/8/2014 | 3/12/2015 |
|
| Transfer Initial Comment Period | 12/9/2014 | 1/9/2015 |
|
| PD Issued | 10/27/2015 | 10/27/2015 |
|
| PD Weekly Public Notice | 11/3/2015 | 11/3/2015 |
|
| Certificate Remaining Issued | 12/17/2015 | 12/17/2015 |
91033 issued supersedes 85943
|
| Final Order Issued | 12/17/2015 | 12/17/2015 |
|
| Completion Due (C Date) | 10/1/2017 | 10/1/2017 |
|
| CBU Received | 8/31/2018 | 8/31/2018 |
|
| CBU Due | 10/1/2018 | 10/1/2018 |
|
| Certificate Confirming Issued | 4/25/2019 | 4/25/2019 |
|