| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/19/2014 | 12/19/2014 |
|
| WMR Request | 12/22/2014 | 1/29/2015 |
|
| GW Review Request | 12/22/2014 | 3/11/2015 |
|
| Reimbursement Authority | 12/23/2014 | 3/31/2015 |
|
| Transfer Initial Comment Period | 12/23/2014 | 1/23/2015 |
|
| RA Applicant Agreement | 2/11/2015 | 2/11/2015 |
|
| WMR Request | 4/1/2015 | 4/1/2015 |
|
| Deficiency Letter | 4/1/2015 | 4/2/2015 |
|
| Draft PD Issued | 4/2/2015 | 5/1/2015 |
|
| News $ Due Letter | 5/20/2015 | 6/15/2015 |
|
| PD Issued | 6/17/2015 | 6/17/2015 |
|
| PD Weekly Public Notice | 6/23/2015 | 6/23/2015 |
|
| Final Order Issued | 8/4/2015 | 8/4/2015 |
|
| CBU Received | 5/31/2016 | 5/31/2016 |
|
| Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
| CBU Due | 10/1/2017 | 10/1/2017 |
|
| Certificate Confirming Issued | 2/5/2021 | 2/5/2021 |
|