| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/22/2014 | 12/22/2014 |
|
| WMR Request | 1/5/2015 | 1/9/2015 |
|
| GW Review Request | 1/5/2015 | 3/6/2015 |
|
| Transfer Initial Comment Period | 1/6/2015 | 2/6/2015 |
|
| Draft PD Issued | 4/16/2015 | 4/16/2015 |
|
| PD Issued | 5/15/2015 | 5/15/2015 |
|
| PD Weekly Public Notice | 5/19/2015 | 5/19/2015 |
|
| Final Order Issued | 6/18/2015 | 6/18/2015 |
|
| Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
| CBU Due | 10/1/2017 | 10/1/2017 |
|
| CBU Received | 11/26/2019 | 11/26/2019 |
|
| Certificate Confirming Issued | 7/29/2022 | 7/29/2022 |
|