| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/22/2015 | 1/22/2015 |
|
| WMR Request | 1/22/2015 | 2/11/2015 |
|
| Transfer Initial Comment Period | 1/27/2015 | 2/27/2015 |
|
| Draft PD Issued | 3/6/2015 | 3/20/2015 |
|
| PD Issued | 3/24/2015 | 3/24/2015 |
|
| PD Weekly Public Notice | 3/31/2015 | 3/31/2015 |
|
| Certificate Remaining Issued | 5/4/2015 | 5/4/2015 |
90218 issued supersedes 89450
|
| Final Order Issued | 5/4/2015 | 5/4/2015 |
|
| Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
| CBU Due | 10/1/2017 | 10/1/2017 |
|
| CBU Received | 11/17/2017 | 11/17/2017 |
|
| Certificate Confirming Issued | 11/21/2018 | 11/21/2018 |
|