Process Step | Date Initiated | Date Completed | Comments |
Received | 2/5/2015 | 2/5/2015 |
|
WMR Request | 2/10/2015 | 10/8/2015 |
|
ODFW Review | 2/10/2015 | 7/16/2015 |
|
Transfer Initial Comment Period | 2/17/2015 | 3/20/2015 |
|
Draft PD Issued | 3/1/2016 | 3/1/2016 |
|
PD Issued | 4/27/2016 | 4/27/2016 |
|
PD Weekly Public Notice | 5/3/2016 | 5/3/2016 |
|
Final Order Issued | 6/23/2016 | 6/23/2016 |
|
Certificate Remaining Issued | 6/23/2016 | |
CERT 91582 ISSUED SUPERSEDES CERT 50801
|
CBU Received | 9/15/2017 | 9/15/2017 |
|
Completion Due (C Date) | 10/1/2017 | 10/1/2017 |
|
CBU Due | 10/1/2018 | 10/1/2018 |
|
Certificate Confirming Issued | 10/15/2021 | 10/15/2021 |
|