Process Step | Date Initiated | Date Completed | Comments |
Received | 2/9/2015 | 2/9/2015 |
|
WMR Request | 2/11/2015 | 6/16/2015 |
|
GW Review Request | 2/11/2015 | 4/8/2015 |
|
Transfer Initial Comment Period | 2/17/2015 | 3/20/2015 |
|
Draft PD Issued | 2/26/2016 | 2/26/2016 |
|
News $ Due Letter | 3/2/2016 | 3/7/2016 |
|
PD Issued | 4/5/2016 | 4/5/2016 |
|
PD Weekly Public Notice | 4/12/2016 | 4/12/2016 |
|
Final Order Issued | 6/23/2016 | 6/23/2016 |
|
Extension Application Received | 6/1/2020 | 6/1/2020 |
|
Extension FO Issued | 6/23/2020 | 6/23/2020 |
|
Extended Completion Date [Extension C Date] | 10/1/2021 | 10/1/2021 |
|
Extension Application Received | 10/4/2021 | 10/4/2021 |
|
Extension FO Issued | 12/13/2021 | 12/13/2021 |
|
Extended Completion Date [Extension C Date] | 10/1/2023 | 10/1/2023 |
|
CBU Received | 9/30/2024 | 9/30/2024 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|