Process Step | Date Initiated | Date Completed | Comments |
Received | 2/19/2015 | 2/19/2015 |
|
WMR Request | 2/23/2015 | 12/4/2015 |
|
ODFW Review | 2/23/2015 | 4/28/2015 |
|
Transfer Initial Comment Period | 3/3/2015 | 4/3/2015 |
|
Draft PD Issued | 8/11/2016 | 8/11/2016 |
|
PD Issued | 9/26/2016 | 9/26/2016 |
|
PD Weekly Public Notice | 10/4/2016 | 10/4/2016 |
|
Final Order Issued | 11/21/2016 | 11/21/2016 |
|
Certificate Remaining Issued | 11/21/2016 | 11/21/2016 |
CERTS: 92069, 92070, 92071, 92077, 92072, 92073, 92074, 92075, 92076
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|
Extension Application Received | 10/18/2023 | 10/18/2023 |
|
Extension FO Issued | 10/30/2024 | 10/30/2024 |
|
Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
CBU Due | 10/1/2027 | 10/1/2027 |
|