| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/27/2015 | 2/27/2015 |
|
| WMR Request | 3/2/2015 | 3/4/2015 |
|
| Transfer Initial Comment Period | 3/3/2015 | 4/3/2015 |
|
| GW Review Request | 11/19/2015 | 12/18/2015 |
|
| GW Review Request | 1/29/2016 | 1/29/2016 |
|
| Draft PD Issued | 3/9/2016 | 3/9/2016 |
|
| PD Issued | 7/5/2016 | 7/5/2016 |
|
| PD Weekly Public Notice | 7/12/2016 | 7/12/2016 |
|
| Final Order Issued | 4/27/2017 | 4/27/2017 |
|
| Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
| CBU Due | 10/1/2022 | 10/1/2022 |
|