Process Step | Date Initiated | Date Completed | Comments |
Received | 3/2/2015 | 3/2/2015 |
|
Reimbursement Authority | 3/2/2015 | 12/17/2015 |
|
WMR Request | 3/9/2015 | 3/26/2015 |
|
ODFW Review | 3/9/2015 | 3/26/2015 |
|
Transfer Initial Comment Period | 3/17/2015 | 4/17/2015 |
|
RA Applicant Agreement | 3/25/2015 | 12/17/2015 |
|
Draft PD Issued | 4/27/2015 | 4/27/2015 |
|
PD Issued | 10/27/2015 | 10/27/2015 |
|
PD Weekly Public Notice | 11/3/2015 | 11/3/2015 |
|
Final Order Issued | 12/17/2015 | 12/17/2015 |
|
Certificate Remaining Issued | 12/17/2015 | 12/17/2015 |
90699 issued supersedes 86961
90700 issued supersedes 86964
|
CBU Received | 10/17/2016 | 10/17/2016 |
|
Certificate Confirming Issued | 5/24/2017 | 5/24/2017 |
|
Completion Due (C Date) | 10/1/2017 | 10/1/2017 |
|
CBU Due | 10/1/2018 | 10/1/2018 |
|