| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/2/2015 | 3/2/2015 |
|
| WMR Request | 3/10/2015 | 3/26/2015 |
|
| Transfer Initial Comment Period | 3/17/2015 | 4/17/2015 |
|
| Draft PD Issued | 6/17/2015 | 8/6/2015 |
|
| PD Issued | 8/6/2015 | 8/6/2015 |
|
| PD Weekly Public Notice | 8/11/2015 | 8/11/2015 |
|
| Final Order Issued | 9/15/2015 | 9/15/2015 |
|
| Certificate Remaining Issued | 9/15/2015 | 9/15/2015 |
90775 issued supersedes 20412
|
| Certificate Remaining Issued | 11/3/2015 | 11/3/2015 |
90927 issued supersedes 90775
|
| Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
| CBU Due | 10/1/2019 | 10/1/2019 |
|
| Extension Application Received | 10/23/2019 | 10/23/2019 |
|
| Extension FO Issued | 11/27/2019 | 11/27/2019 |
|
| Extended Completion Date [Extension C Date] | 10/1/2021 | 10/1/2021 |
|
| CBU Completeness Review | 1/21/2022 | 1/28/2022 |
|
| CBU Received | 1/21/2022 | 1/21/2022 |
|
| Certificate Confirming Issued | 9/9/2022 | 9/9/2022 |
|
| CBU Due | 10/1/2022 | 10/1/2022 |
|