| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/10/2015 | 3/10/2015 |
|
| WMR Request | 3/12/2015 | 4/8/2015 |
|
| GW Review Request | 3/12/2015 | 6/11/2015 |
|
| Transfer Initial Comment Period | 3/17/2015 | 4/17/2015 |
|
| PD Issued | 10/27/2015 | 10/27/2015 |
|
| PD Weekly Public Notice | 11/3/2015 | 11/3/2015 |
|
| Certificate Remaining Issued | 12/24/2015 | 12/24/2015 |
91078 issued supersedes 26990
|
| Final Order Issued | 12/24/2015 | 12/24/2015 |
|
| CBU Received | 11/10/2016 | 11/10/2016 |
|
| Completion Due (C Date) | 10/1/2017 | 10/1/2017 |
|
| CBU Due | 10/1/2018 | 10/1/2018 |
|
| Proposed Certificate Mailing | 7/16/2021 | 7/16/2021 |
|
| Certificate Confirming Issued | 12/3/2021 | 12/3/2021 |
|