Process Step | Date Initiated | Date Completed | Comments |
Received | 4/16/2015 | 4/16/2015 |
|
Reimbursement Authority | 4/23/2015 | 8/14/2015 |
|
WMR Request | 4/23/2015 | 4/28/2015 |
|
GW Review Request | 4/23/2015 | 8/14/2015 |
|
Transfer Initial Comment Period | 4/28/2015 | 5/29/2015 |
|
Draft PD Issued | 4/4/2016 | 4/4/2016 |
|
PD Issued | 4/21/2016 | 4/21/2016 |
|
PD Weekly Public Notice | 4/26/2016 | 4/26/2016 |
|
Final Order Issued | 5/31/2016 | 5/31/2016 |
|
Completion Due (C Date) | 10/1/2017 | 10/1/2017 |
|
CBU Received | 11/21/2017 | 11/21/2017 |
|
CBU Due | 10/1/2018 | 10/1/2018 |
|
Certificate Confirming Issued | 10/27/2020 | 10/27/2020 |
CF Cert 95332 Issued supersedes Cert 68265
|
Final Order Issued | 10/27/2020 | 10/27/2020 |
|