Process Step | Date Initiated | Date Completed | Comments |
Received | 5/20/2015 | 5/20/2015 |
|
Reimbursement Authority | 5/20/2015 | |
|
WMR Request | 5/26/2015 | 5/28/2015 |
|
Transfer Initial Comment Period | 6/2/2015 | 7/3/2015 |
|
RA Applicant Agreement | 6/25/2015 | 6/25/2015 |
|
Draft PD Issued | 7/22/2015 | 7/22/2015 |
|
PD Issued | 8/24/2015 | 8/24/2015 |
|
PD Weekly Public Notice | 8/25/2015 | 8/25/2015 |
|
Certificate Remaining Issued | 9/28/2015 | 9/28/2015 |
90729 issued supersedes 27019
|
Final Order Issued | 9/28/2015 | 9/28/2015 |
|
Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
CBU Due | 10/1/2017 | 10/1/2017 |
|
CBU Received | 11/4/2019 | 11/4/2019 |
|
Certificate Confirming Issued | 11/12/2021 | 11/12/2021 |
|