Process Step | Date Initiated | Date Completed | Comments |
Received | 6/11/2015 | 6/11/2015 |
|
WMR Request | 6/15/2015 | 3/29/2017 |
|
ODFW Review | 6/15/2015 | 7/22/2015 |
|
Reimbursement Authority | 6/16/2015 | 9/16/2016 |
|
Transfer Initial Comment Period | 6/16/2015 | 7/17/2015 |
|
RA Applicant Agreement | 7/13/2015 | 7/13/2015 |
|
Administrative Hold | 8/5/2015 | 12/9/2016 |
|
Transfer Initial Comment Period | 2/21/2017 | 3/24/2017 |
|
PD Issued | 4/26/2019 | 4/26/2019 |
|
PD Weekly Public Notice | 4/30/2019 | 4/30/2019 |
|
Final Order Issued | 6/21/2019 | 6/21/2019 |
|
Final Order Issued | 7/31/2019 | 7/31/2019 |
|
Final Order Issued | 10/28/2019 | 10/28/2019 |
|
CBU Completeness Review | 1/12/2021 | 1/27/2021 |
|
CBU Received | 1/12/2021 | 1/12/2021 |
|
Proposed Certificate Mailing | 7/3/2023 | 7/3/2023 |
|
Certificate Confirming Issued | 9/1/2023 | 9/1/2023 |
|