Process Step | Date Initiated | Date Completed | Comments |
Received | 6/16/2015 | 6/16/2015 |
|
WMR Request | 6/18/2015 | 9/16/2015 |
|
Transfer Initial Comment Period | 6/23/2015 | 7/24/2015 |
|
Draft PD Issued | 11/13/2015 | 11/13/2015 |
|
PD Issued | 3/31/2016 | 3/31/2016 |
|
PD Weekly Public Notice | 4/5/2016 | 4/5/2016 |
|
Certificate Remaining Issued | 10/21/2016 | |
CERT 92002 ISSUED SUPERSEDES CERT 47816
|
Final Order Issued | 10/21/2016 | 10/21/2016 |
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|