| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/31/2015 | 7/31/2015 |
|
| GW Review Request | 8/3/2015 | 12/9/2015 |
|
| WMR Request | 8/3/2015 | 10/9/2015 |
|
| Transfer Initial Comment Period | 8/4/2015 | 9/4/2015 |
|
| Draft PD Issued | 3/23/2016 | 7/26/2016 |
|
| News $ Due Letter | 8/10/2016 | 8/12/2016 |
|
| PD Issued | 8/22/2016 | 8/22/2016 |
|
| PD Weekly Public Notice | 8/23/2016 | 8/23/2016 |
|
| Final Order Issued | 10/21/2016 | 10/21/2016 |
|
| Extension Application Received | 9/11/2017 | |
|
| Extension FO Issued | 9/27/2017 | 9/27/2017 |
|
| Completion Due (C Date) | 10/1/2017 | 10/1/2017 |
|
| CBU Due | 10/1/2018 | 10/1/2018 |
|
| CBU Received | 11/15/2018 | 11/15/2018 |
|
| Certificate Confirming Issued | 4/5/2019 | 4/5/2019 |
|