Process Step | Date Initiated | Date Completed | Comments |
Received | 8/4/2015 | 8/4/2015 |
|
WMR Request | 8/6/2015 | 8/17/2015 |
|
ODFW Review | 8/6/2015 | 11/23/2015 |
|
Transfer Initial Comment Period | 8/11/2015 | 9/11/2015 |
|
PD Issued | 6/20/2016 | 6/20/2016 |
|
PD Weekly Public Notice | 6/28/2016 | 6/28/2016 |
|
Certificate Remaining Issued | 8/11/2016 | |
Cert 91770 Issued supersedes Cert 1828
|
Final Order Issued | 8/11/2016 | 8/11/2016 |
|
Completion Due (C Date) | 10/1/2017 | 10/1/2017 |
|
CBU Received | 3/19/2018 | 3/19/2018 |
|
CBU Due | 10/1/2018 | 10/1/2018 |
|
Certificate Confirming Issued | 6/11/2021 | 6/11/2021 |
|