| Process Step | Date Initiated | Date Completed | Comments |
| Received | 8/10/2015 | 8/10/2015 |
|
| WMR Request | 8/12/2015 | 1/12/2016 |
|
| Transfer Initial Comment Period | 8/18/2015 | 9/18/2015 |
|
| Draft PD Issued | 2/29/2016 | 2/29/2016 |
|
| PD Issued | 7/22/2016 | 7/22/2016 |
|
| PD Weekly Public Notice | 7/26/2016 | 7/26/2016 |
|
| Final Order Issued | 9/12/2016 | 9/12/2016 |
|
| Certificate Remaining Issued | 9/12/2016 | |
CERT 91879 ISSUED SUPERSEDES CERT 439
|
| Certificate Remaining Issued | 9/12/2016 | |
CERT 91880 ISSUED SUPERSEDES CERT 4931
|
| Completion Due (C Date) | 10/1/2017 | 10/1/2017 |
|
| CBU Received | 3/5/2018 | 3/5/2018 |
|
| CBU Due | 10/1/2018 | 10/1/2018 |
|
| Certificate Confirming Issued | 3/26/2021 | 3/26/2021 |
|