| Process Step | Date Initiated | Date Completed | Comments | 
				| Received | 9/4/2015 | 9/4/2015 |  | 
				| WMR Request | 9/10/2015 | 11/9/2015 |  | 
				| ODFW Review | 9/10/2015 | 12/7/2015 |  | 
				| Transfer Initial Comment Period | 9/15/2015 | 10/16/2015 |  | 
				| Draft PD Issued | 3/29/2016 | 4/4/2016 |  | 
				| PD Issued | 4/15/2016 | 4/15/2016 |  | 
				| PD Weekly Public Notice | 4/26/2016 | 4/26/2016 |  | 
				| Final Order Issued | 10/7/2016 | 10/7/2016 |  | 
				| Certificate Remaining Issued | 10/7/2016 |  | CERT 91903 ISSUED SUPERSEDES CERT 86120 | 
				| CBU Received | 8/24/2017 | 8/24/2017 |  | 
				| Completion Due (C Date) | 10/1/2017 | 10/1/2017 |  | 
				| CBU Due | 10/1/2018 | 10/1/2018 |  | 
				| Certificate Confirming Issued | 3/26/2021 | 3/26/2021 |  |