Process Step | Date Initiated | Date Completed | Comments |
Received | 10/27/2015 | 10/27/2015 |
|
WMR Request | 11/2/2015 | 11/10/2015 |
|
GW Review Request | 11/2/2015 | 2/5/2016 |
|
Transfer Initial Comment Period | 11/3/2015 | 12/4/2015 |
|
Draft PD Issued | 4/13/2016 | 4/13/2016 |
|
PD Issued | 6/3/2016 | 6/3/2016 |
|
PD Weekly Public Notice | 6/7/2016 | 6/7/2016 |
|
Final Order Issued | 8/18/2017 | 8/18/2017 |
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
Final Order Issued | 3/15/2023 | 3/15/2023 |
Partial reversion of change in POA and amending SO V. 105 P. 639-645.
|
CBU Received | 4/14/2023 | 4/14/2023 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|
Certificate Confirming Issued | 6/14/2024 | 6/14/2024 |
|