| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/30/2015 | 11/30/2015 |
|
| WMR Request | 12/1/2015 | 12/14/2015 |
|
| GW Review Request | 12/1/2015 | 12/2/2015 |
|
| Transfer Initial Comment Period | 12/8/2015 | 1/8/2016 |
|
| PD Issued | 2/22/2016 | 2/22/2016 |
|
| PD Weekly Public Notice | 3/1/2016 | 3/1/2016 |
|
| Certificate Remaining Issued | 4/15/2016 | 4/15/2016 |
CERT 91392 ISSUED SUPERSEDES CERT 52875
|
| Certificate Remaining Issued | 4/15/2016 | 4/15/2016 |
CERT 91393 ISSUED SUPERSEDES CERT 76941
|
| Final Order Issued | 4/15/2016 | 4/15/2016 |
|
| CBU Received | 4/24/2020 | 4/24/2020 |
|
| Certificate Confirming Issued | 9/3/2020 | 9/3/2020 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|