Process Step | Date Initiated | Date Completed | Comments |
Received | 12/10/2015 | 12/10/2015 |
|
Reimbursement Authority | 12/10/2015 | 3/31/2016 |
|
WMR Request | 12/14/2015 | 12/15/2015 |
|
GW Review Request | 12/14/2015 | 3/16/2016 |
|
Transfer Initial Comment Period | 12/15/2015 | 1/15/2016 |
|
Draft PD Issued | 6/16/2017 | 6/16/2017 |
|
PD Issued | 10/11/2017 | 10/11/2017 |
|
PD Weekly Public Notice | 10/17/2017 | 10/17/2017 |
|
Final Order Issued | 11/21/2017 | 11/21/2017 |
|
Certificate Remaining Issued | 11/21/2017 | |
CERT 93398 ISSUED SUPERSEDES CERT 90952
|
CBU Received | 4/6/2023 | 4/6/2023 |
|
Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
Certificate Confirming Issued | 11/17/2023 | 11/17/2023 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|