| Process Step | Date Initiated | Date Completed | Comments | 
			
				| Received | 1/19/2016 | 1/19/2016 | 
                                                    
                                                 | 
			
				| ODFW Review | 1/22/2016 | 5/4/2016 | 
                                                    
                                                 | 
			
				| WMR Request | 1/22/2016 | 2/5/2016 | 
                                                    
                                                 | 
			
				| Transfer Initial Comment Period | 1/26/2016 | 2/26/2016 | 
                                                    
                                                 | 
			
				| Draft PD Issued | 4/6/2017 | 4/6/2017 | 
                                                    
                                                 | 
			
				| PD Issued | 5/16/2017 | 5/16/2017 | 
                                                    
                                                 | 
			
				| PD Weekly Public Notice | 5/23/2017 | 5/23/2017 | 
                                                    
                                                 | 
			
				| Final Order Issued | 8/14/2018 | 8/14/2018 | 
                                                    
                                                 | 
			
				| Certificate Remaining Issued | 8/14/2018 | 8/14/2018 | 
                                                    RR 93953 supersedes 45563
                                                 | 
			
				| Extension Application Received | 9/25/2019 | 9/25/2019 | 
                                                    
                                                 | 
			
				| Completion Due (C Date) | 10/1/2019 | 10/1/2019 | 
                                                    
                                                 | 
			
				| Extension FO Issued | 10/3/2019 | 10/3/2019 | 
                                                    
                                                 | 
			
				| Extended Completion Date [Extension C Date] | 10/1/2020 | 10/1/2020 | 
                                                    
                                                 | 
			
				| CBU Due | 10/1/2020 | 10/1/2020 | 
                                                    
                                                 | 
			
				| CBU Completeness Review | 8/20/2021 | 9/10/2021 | 
                                                    
                                                 | 
			
				| CBU Received | 8/20/2021 | 8/20/2021 | 
                                                    
                                                 | 
			
				| CBU Due | 10/1/2021 | 10/1/2021 | 
                                                    
                                                 | 
			
				| Certificate Confirming Issued | 7/21/2023 | 7/21/2023 | 
                                                    
                                                 |