| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/19/2016 | 1/19/2016 |
|
| ODFW Review | 1/22/2016 | 5/4/2016 |
|
| WMR Request | 1/22/2016 | 2/5/2016 |
|
| Transfer Initial Comment Period | 1/26/2016 | 2/26/2016 |
|
| Draft PD Issued | 4/6/2017 | 4/6/2017 |
|
| PD Issued | 5/16/2017 | 5/16/2017 |
|
| PD Weekly Public Notice | 5/23/2017 | 5/23/2017 |
|
| Final Order Issued | 8/14/2018 | 8/14/2018 |
|
| Certificate Remaining Issued | 8/14/2018 | 8/14/2018 |
RR 93953 supersedes 45563
|
| Extension Application Received | 9/25/2019 | 9/25/2019 |
|
| Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
| Extension FO Issued | 10/3/2019 | 10/3/2019 |
|
| Extended Completion Date [Extension C Date] | 10/1/2020 | 10/1/2020 |
|
| CBU Due | 10/1/2020 | 10/1/2020 |
|
| CBU Completeness Review | 8/20/2021 | 9/10/2021 |
|
| CBU Received | 8/20/2021 | 8/20/2021 |
|
| CBU Due | 10/1/2021 | 10/1/2021 |
|
| Certificate Confirming Issued | 7/21/2023 | 7/21/2023 |
|