Process Step | Date Initiated | Date Completed | Comments |
Received | 2/4/2016 | 2/4/2016 |
|
WMR Request | 2/5/2016 | 3/8/2016 |
|
GW Review Request | 2/5/2016 | 3/10/2016 |
|
Transfer Initial Comment Period | 2/9/2016 | 3/11/2016 |
|
PD Issued | 5/16/2017 | 5/16/2017 |
|
PD Weekly Public Notice | 5/23/2017 | 5/23/2017 |
|
Final Order Issued | 7/6/2017 | 7/6/2017 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
CBU Received | 8/12/2020 | 8/12/2020 |
|
Certificate Confirming Issued | 3/5/2021 | 3/5/2021 |
|