| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/1/2016 | 3/1/2016 |
|
| WMR Request | 3/10/2016 | 3/15/2016 |
|
| GW Review Request | 3/10/2016 | 4/26/2016 |
|
| Transfer Initial Comment Period | 3/15/2016 | 4/15/2016 |
|
| PD Issued | 8/14/2019 | 8/14/2019 |
|
| PD Weekly Public Notice | 8/20/2019 | 8/20/2019 |
|
| Final Order Issued | 1/8/2020 | 1/8/2020 |
|
| CBU Received | 6/8/2021 | 6/8/2021 |
|
| Certificate Confirming Issued | 10/15/2021 | 10/15/2021 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|