| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/2/2016 | 3/2/2016 |
|
| WMR Request | 3/11/2016 | 3/14/2016 |
|
| ODFW Review | 3/11/2016 | 4/4/2016 |
|
| Transfer Initial Comment Period | 3/15/2016 | 4/15/2016 |
|
| PD Issued | 2/21/2017 | 2/21/2017 |
|
| PD Weekly Public Notice | 2/28/2017 | 2/28/2017 |
|
| Final Order Issued | 4/12/2017 | 4/12/2017 |
|
| CBU Received | 8/27/2019 | 8/27/2019 |
|
| Final Order Issued | 8/29/2019 | 8/29/2019 |
|
| Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
| Certificate Confirming Issued | 12/27/2019 | 12/27/2019 |
|
| CBU Due | 10/1/2020 | 10/1/2020 |
|