| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/11/2016 | 3/11/2016 |
|
| WMR Request | 3/18/2016 | 4/14/2016 |
|
| ODFW Review | 3/18/2016 | 4/28/2016 |
|
| Transfer Initial Comment Period | 3/22/2016 | 4/22/2016 |
|
| PD Issued | 10/9/2017 | 10/9/2017 |
|
| PD Weekly Public Notice | 10/17/2017 | 10/17/2017 |
|
| Certificate Remaining Issued | 12/22/2017 | 12/22/2017 |
CERT 93366 ISSUED SUPERSEDES CERT 31321
|
| Final Order Issued | 12/22/2017 | 12/22/2017 |
|
| CBU Completeness Review | 11/16/2020 | 11/20/2020 |
|
| CBU Received | 11/16/2020 | 11/16/2020 |
|
| Certificate Confirming Issued | 9/8/2023 | 9/8/2023 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|