Process Step | Date Initiated | Date Completed | Comments |
Received | 3/16/2016 | 3/16/2016 |
|
GW Review Request | 3/18/2016 | 8/29/2016 |
|
WMR Request | 3/18/2016 | 4/11/2016 |
|
Transfer Initial Comment Period | 3/22/2016 | 4/22/2016 |
|
PD Issued | 2/7/2017 | 2/7/2017 |
|
PD Weekly Public Notice | 2/14/2017 | 2/14/2017 |
|
Final Order Issued | 4/12/2017 | 4/12/2017 |
|
CBU Received | 6/7/2018 | 6/7/2018 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
Certificate Confirming Issued | 4/28/2023 | 4/28/2023 |
|