Process Step | Date Initiated | Date Completed | Comments |
Received | 3/28/2016 | 3/28/2016 |
|
WMR Request | 3/29/2016 | 3/30/2016 |
|
Transfer Initial Comment Period | 4/5/2016 | 5/6/2016 |
|
PD Issued | 6/7/2017 | 6/7/2017 |
|
PD Weekly Public Notice | 6/13/2017 | 6/13/2017 |
|
Final Order Issued | 7/24/2017 | 7/24/2017 |
|
CBU Received | 5/11/2018 | 5/11/2018 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
Certificate Confirming Issued | 3/26/2021 | 3/26/2021 |
|