| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/30/2016 | 3/30/2016 |
|
| WMR Request | 4/5/2016 | 4/5/2016 |
|
| Transfer Initial Comment Period | 4/12/2016 | 5/13/2016 |
|
| Draft PD Issued | 5/27/2016 | 5/27/2016 |
|
| PD Issued | 9/15/2016 | 9/15/2016 |
|
| PD Weekly Public Notice | 9/20/2016 | 9/20/2016 |
|
| Certificate Remaining Issued | 10/21/2016 | |
CERT 92003 ISSUED SUPERSEDES CERT 66862
|
| Final Order Issued | 10/21/2016 | 10/21/2016 |
|
| CBU Received | 10/30/2017 | 10/30/2017 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| Certificate Confirming Issued | 6/16/2023 | 6/16/2023 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|