Process Step | Date Initiated | Date Completed | Comments |
Received | 4/12/2016 | 4/12/2016 |
|
Reimbursement Authority | 4/12/2016 | 1/23/2017 |
|
WMR Request | 4/20/2016 | 5/16/2016 |
|
GW Review Request | 4/20/2016 | 6/2/2016 |
|
Transfer Initial Comment Period | 4/26/2016 | 5/27/2016 |
|
RA Applicant Agreement | 5/16/2016 | 5/16/2016 |
|
PD Issued | 12/15/2016 | 12/15/2016 |
|
PD Weekly Public Notice | 12/20/2016 | 12/20/2016 |
|
Final Order Issued | 1/31/2017 | 1/31/2017 |
|
CBU Received | 7/24/2017 | 7/24/2017 |
|
Proposed Certificate Mailing | 1/25/2018 | 1/25/2018 |
|
Certificate Confirming Issued | 8/8/2018 | 8/8/2018 |
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|