| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/25/2016 | 4/25/2016 |
|
| WMR Request | 4/28/2016 | 5/16/2016 |
|
| Transfer Initial Comment Period | 5/3/2016 | 6/3/2016 |
|
| Draft PD Issued | 8/16/2016 | 8/16/2016 |
|
| PD Issued | 8/18/2017 | 8/18/2017 |
|
| PD Weekly Public Notice | 8/29/2017 | 8/29/2017 |
|
| Final Order Issued | 9/29/2017 | 9/29/2017 |
|
| CBU Due | 9/29/2017 | 9/29/2017 |
|
| Completion Due (C Date) | 9/29/2017 | 9/29/2017 |
|
| CBU Received | 12/18/2017 | 12/18/2017 |
|
| Certificate Confirming Issued | 11/6/2020 | 11/6/2020 |
|