Process Step | Date Initiated | Date Completed | Comments |
Received | 4/18/2016 | 4/18/2016 |
|
WMR Request | 4/29/2016 | 7/13/2016 |
|
GW Review Request | 4/29/2016 | 6/1/2016 |
|
Transfer Initial Comment Period | 5/3/2016 | 6/3/2016 |
|
Draft PD Issued | 6/20/2016 | 6/20/2016 |
|
Draft PD Issued | 7/25/2016 | 7/25/2016 |
|
PD Issued | 5/1/2017 | 5/1/2017 |
|
PD Weekly Public Notice | 5/9/2017 | 5/9/2017 |
|
Final Order Issued | 6/22/2017 | 6/22/2017 |
|
CBU Completeness Review | 8/26/2020 | 9/14/2020 |
|
CBU Received | 8/26/2020 | 8/26/2020 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|
Proposed Certificate Mailing | 12/16/2022 | 12/16/2022 |
|
Certificate Confirming Issued | 9/1/2023 | 9/1/2023 |
|