Process Step | Date Initiated | Date Completed | Comments |
Received | 4/29/2016 | 4/29/2016 |
|
GW Review Request | 5/2/2016 | 8/18/2016 |
|
WMR Request | 5/2/2016 | 5/10/2016 |
|
Transfer Initial Comment Period | 5/3/2016 | 6/3/2016 |
|
Draft PD Issued | 1/9/2017 | 1/9/2017 |
|
PD Issued | 7/6/2017 | 7/6/2017 |
|
PD Weekly Public Notice | 7/11/2017 | 7/11/2017 |
|
Final Order Issued | 8/16/2017 | 8/16/2017 |
|
Extension Application Received | 9/14/2018 | 9/14/2018 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
Extension FO Issued | 10/9/2018 | 10/9/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
CBU Received | 10/28/2020 | 10/28/2020 |
|
Certificate Confirming Issued | 3/16/2021 | 3/16/2021 |
|
Certificate Confirming Issued | 4/30/2021 | 4/30/2021 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|