Process Step | Date Initiated | Date Completed | Comments |
Received | 5/16/2016 | 5/16/2016 |
|
ODFW Review | 5/19/2016 | 6/9/2016 |
|
WMR Request | 5/19/2016 | 6/3/2016 |
|
Transfer Initial Comment Period | 5/24/2016 | 6/24/2016 |
|
Deficiency Letter | 7/19/2019 | 7/19/2019 |
|
Deficiency Letter | 8/20/2019 | 8/20/2019 |
|
Administrative Hold | 10/26/2019 | 12/26/2019 |
|
Draft PD Issued | 1/7/2020 | 1/8/2020 |
|
News $ Due Letter | 2/27/2020 | 3/9/2020 |
|
PD Issued | 6/4/2020 | 6/4/2020 |
|
PD Weekly Public Notice | 6/9/2020 | 6/9/2020 |
|
Final Order Issued | 8/10/2020 | 8/10/2020 |
|
Certificate Remaining Issued | 8/10/2020 | 8/10/2020 |
RR 95032 Issued Supersedes Cert 2730
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|