Process Step | Date Initiated | Date Completed | Comments |
Received | 5/16/2016 | 5/16/2016 |
|
WMR Request | 5/19/2016 | 6/3/2016 |
|
GW Review Request | 5/19/2016 | 6/10/2016 |
|
Transfer Initial Comment Period | 5/24/2016 | 6/24/2016 |
|
Draft PD Issued | 9/22/2017 | 9/22/2017 |
|
PD Issued | 4/5/2018 | 4/5/2018 |
|
PD Weekly Public Notice | 4/10/2018 | 4/10/2018 |
|
Final Order Issued | 11/14/2018 | 11/14/2018 |
|
Certificate Remaining Issued | 11/14/2018 | 11/14/2018 |
RR 93776 Issued Supersedes Cert 86190
|
Certificate Remaining Issued | 11/14/2018 | 11/14/2018 |
RR 93777 Issued Supersedes Cert 88583
|
Certificate Remaining Issued | 11/14/2018 | 11/14/2018 |
RR 93778 Issued Supersedes Cert 88584
|
CBU Completeness Review | 9/8/2020 | 9/15/2020 |
|
CBU Received | 9/8/2020 | 9/8/2020 |
|
Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|
Certificate Confirming Issued | 6/19/2023 | 6/19/2023 |
|