| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/19/2016 | 5/19/2016 |
|
| WMR Request | 5/26/2016 | 6/2/2016 |
|
| Transfer Initial Comment Period | 5/31/2016 | 7/1/2016 |
|
| GW Review Request | 6/2/2016 | 8/22/2016 |
|
| Draft PD Issued | 8/22/2018 | 8/22/2018 |
|
| Deficiency Letter | 2/7/2020 | 3/30/2021 |
|
| PD Issued | 7/29/2020 | 7/29/2020 |
|
| PD Weekly Public Notice | 8/4/2020 | 8/4/2020 |
|
| Final Order Issued | 3/30/2021 | 3/30/2021 |
|
| Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| CBU Due | 10/1/2022 | 10/1/2022 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|