Process Step | Date Initiated | Date Completed | Comments |
Received | 6/9/2016 | 6/9/2016 |
|
WMR Request | 6/13/2016 | 6/27/2016 |
|
GW Review Request | 6/13/2016 | 12/22/2016 |
|
Transfer Initial Comment Period | 6/14/2016 | 7/15/2016 |
|
Draft PD Issued | 2/23/2017 | 2/23/2017 |
|
PD Issued | 3/23/2017 | 3/23/2017 |
|
PD Weekly Public Notice | 3/28/2017 | 3/28/2017 |
|
Final Order Issued | 5/18/2017 | 5/18/2017 |
|
Certificate Remaining Issued | 5/18/2017 | |
CERT 93118 ISSUED SUPSERSEDES CERT 82906
|
Certificate Remaining Issued | 6/27/2017 | |
CERT 93201 ISSUED SUPERSEDES CERT 93118
|
Final Order Issued | 6/27/2017 | 6/27/2017 |
|
CBU Received | 7/31/2017 | 7/31/2017 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
Certificate Confirming Issued | 3/26/2021 | 3/26/2021 |
|