Process Step | Date Initiated | Date Completed | Comments |
Received | 6/20/2016 | 6/20/2016 |
|
WMR Request | 6/22/2016 | 8/16/2016 |
|
GW Review Request | 6/22/2016 | 3/23/2017 |
|
Transfer Initial Comment Period | 6/28/2016 | 7/29/2016 |
|
Draft PD Issued | 6/27/2017 | 6/27/2017 |
|
PD Issued | 9/7/2017 | 9/7/2017 |
|
PD Weekly Public Notice | 9/12/2017 | 9/12/2017 |
|
Final Order Issued | 10/25/2017 | 10/25/2017 |
|
CBU Received | 10/7/2020 | 10/7/2020 |
|
Certificate Confirming Issued | 4/9/2021 | 4/9/2021 |
|
Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|