Process Step | Date Initiated | Date Completed | Comments |
Received | 6/30/2016 | 6/30/2016 |
|
GW Review Request | 7/5/2016 | 12/22/2016 |
|
WMR Request | 7/5/2016 | 8/5/2016 |
|
Transfer Initial Comment Period | 7/12/2016 | 8/12/2016 |
|
Draft PD Issued | 4/12/2017 | 4/12/2017 |
|
PD Issued | 5/1/2017 | 5/1/2017 |
|
PD Weekly Public Notice | 5/9/2017 | 5/9/2017 |
|
Final Order Issued | 6/14/2017 | 6/14/2017 |
|
Certificate Remaining Issued | 6/14/2017 | |
CERT 93196 ISSUED SUPERSEDES CERT 37640
|
CBU Received | 9/14/2017 | 9/14/2017 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
Certificate Confirming Issued | 8/25/2023 | 8/25/2023 |
|
Certificate Confirming Issued | 10/23/2023 | 10/23/2023 |
|