Process Step | Date Initiated | Date Completed | Comments |
Received | 7/27/2016 | 7/27/2016 |
|
GW Review Request | 8/2/2016 | 4/21/2017 |
|
WMR Request | 8/2/2016 | 8/5/2016 |
|
Transfer Initial Comment Period | 8/9/2016 | 9/9/2016 |
|
Draft PD Issued | 5/19/2017 | 5/19/2017 |
|
PD Issued | 6/7/2017 | 6/7/2017 |
|
PD Weekly Public Notice | 6/13/2017 | 6/13/2017 |
|
Final Order Issued | 7/31/2017 | 7/31/2017 |
|
Certificate Remaining Issued | 7/31/2017 | |
CERT 93280 ISSUED SUPERSEDES CERT 44105
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
Extension Application Received | 10/16/2018 | 10/16/2018 |
|
Extension FO Issued | 11/1/2018 | 11/1/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
CBU Received | 5/18/2020 | 5/18/2020 |
|
Extended Completion Date [Extension C Date] | 10/1/2020 | 10/1/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|
Proposed Certificate Mailing | 9/24/2024 | 9/24/2024 |
|