Process Step | Date Initiated | Date Completed | Comments |
Received | 7/29/2016 | 7/29/2016 |
|
WMR Request | 8/3/2016 | 2/3/2017 |
|
Transfer Initial Comment Period | 8/9/2016 | 9/9/2016 |
|
Draft PD Issued | 12/12/2017 | 12/12/2017 |
|
WMR Request | 12/15/2017 | 12/15/2017 |
|
PD Issued | 3/22/2018 | 3/22/2018 |
|
PD Weekly Public Notice | 3/27/2018 | 3/27/2018 |
|
Final Order Issued | 5/9/2018 | 5/9/2018 |
|
Final Order Issued | 6/18/2018 | 6/18/2018 |
|
Completion Due (C Date) | 10/1/2028 | 10/1/2028 |
|
CBU Due | 10/1/2029 | 10/1/2029 |
|