Process Step | Date Initiated | Date Completed | Comments |
Received | 9/14/2016 | 9/14/2016 |
|
WMR Request | 9/16/2016 | 9/19/2016 |
|
Transfer Initial Comment Period | 9/20/2016 | 10/21/2016 |
|
PD Issued | 3/6/2017 | 3/6/2017 |
|
PD Weekly Public Notice | 3/7/2017 | 3/7/2017 |
|
Final Order Issued | 4/17/2017 | 4/17/2017 |
|
Certificate Remaining Issued | 4/17/2017 | 4/17/2017 |
CERT 92978 ISSUED SUPERSEDES CERT 91806
|
Extension Application Received | 9/18/2020 | 9/18/2020 |
|
Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
Extension FO Issued | 11/18/2020 | 11/18/2020 |
|
CBU Received | 12/7/2020 | 12/7/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|
Extended Completion Date [Extension C Date] | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|
Certificate Confirming Issued | 2/10/2023 | 2/10/2023 |
|