| Process Step | Date Initiated | Date Completed | Comments |
| Received | 9/19/2016 | 9/19/2016 |
|
| WMR Request | 9/23/2016 | 9/27/2016 |
|
| GW Review Request | 9/23/2016 | 8/29/2017 |
|
| Transfer Initial Comment Period | 9/27/2016 | 10/28/2016 |
|
| Draft PD Issued | 10/3/2017 | 10/3/2017 |
|
| PD Issued | 12/7/2017 | 12/7/2017 |
|
| PD Weekly Public Notice | 12/12/2017 | 12/12/2017 |
|
| Final Order Issued | 1/31/2018 | 1/31/2018 |
|
| CBU Received | 10/22/2018 | 10/22/2018 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| Certificate Confirming Issued | 10/6/2023 | 10/6/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|