Process Step | Date Initiated | Date Completed | Comments |
CBU Received | 9/27/2006 | 9/27/2006 |
|
Received | 9/26/2016 | 9/26/2016 |
|
WMR Request | 9/30/2016 | 10/24/2016 |
|
GW Review Request | 9/30/2016 | 10/28/2016 |
|
Transfer Initial Comment Period | 10/4/2016 | 11/4/2016 |
|
Draft PD Issued | 2/9/2017 | 2/9/2017 |
|
PD Issued | 4/4/2017 | 4/4/2017 |
|
Final Order Issued | 5/18/2017 | 5/18/2017 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
CBU Received | 8/15/2022 | 8/15/2022 |
|
Certificate Confirming Issued | 8/11/2023 | 8/11/2023 |
|